Fastest Built F60 Store on Stilts within Tesco Estate Worldwide.

Full BIM Implementation

Added Value:

This project was Fastest Built F60 Store of its kind within the Tesco Estate Worldwide.

PCL took complete ownership of this Design and Build project. By running through BIM and collaborating with all parties from inception to completion, PCL successfully delivered the new Shopping Centre within budget, four months earlier than initial projected timelines.

Contract Value:     €22 million

Works Complete: August 2014

 

http://precisionconstruction.ie/wp-content/uploads/2017/11/IMG_3955-1000x600.jpg
http://precisionconstruction.ie/wp-content/uploads/2017/11/IMG_4063-1000x600.jpg
http://precisionconstruction.ie/wp-content/uploads/2017/11/IMG_4151-1000x600.jpg
http://precisionconstruction.ie/wp-content/uploads/2017/11/IMG_3932-1000x600.jpg
http://precisionconstruction.ie/wp-content/uploads/2017/11/IMG_4211-1000x600.jpg

Project Overview

Address

Ramparts Road, Dundalk, Co. Louth.

Project

New commercial development including Shop Units and Petrol Filling Station (PFS) consisting of demolition of existing Shopping Centre, PFS and decontamination works.

Description Of Featured Works

  • Construction of Temporary Units & Independent Access
  • Demolition of existing Centre & PFS including decontamination works
  • Opening of Existing Culvert to form new feature.
  • Construction of a new Commercial Building on stilts & associated site works & amenities.

Duration Of Featured Project

December 2013 to August 2014

http://precisionconstruction.ie/wp-content/uploads/2017/11/233_Tesco_Logo-700x350.png