Construction of Shopping Centre, Tesco Format 80 Supermarket and associated Site Works.
Added Value:
Structural steelwork was prefabricated over holiday period, ready for erection when works resumed post Christmas. Substructure design was also changed to stone piling to accelerate programme.
PCL delivered the project in 2 phases, allowing the shopping centre to commence trading and provide early investment return. This required PCL to work within a trading environment, managing safety and security while providing customers with a high quality shopping experience.
Contract Value: €26 million
Works Complete:
Phase 1 - November 2010
Phase 2 - July 2011





Project Overview
Address
St. David’s CBS, Artane, Dublin 5.
Project
Remedial works to Facades as Part of On-going Maintenance Contract Including Capital Upgrade and Remediation Projects to a Listed Building
Description Of Featured Works
Remedial repair works to rendering on external elevations, painting and decoration and replacement of water tanks to listed building at St. David’s CBS, Artane, Dublin 5.
Duration Of Featured Project
September 2009 to November 2009