Construction of Shopping Centre, Tesco Format 80 Supermarket and associated Site Works.

Added Value:

Structural steelwork was prefabricated over holiday period, ready for erection when works resumed post Christmas. Substructure design was also changed to stone piling to accelerate programme.

PCL delivered the project in 2 phases, allowing the shopping centre to commence trading and provide early investment return. This required PCL to work within a trading environment, managing safety and security while providing customers with a high quality shopping experience.

Contract Value:    €26 million

Works Complete:

Phase 1 - November 2010

Phase 2 - July 2011

 

http://precisionconstruction.ie/wp-content/uploads/2017/11/IMG_2295-1000x600.jpg
http://precisionconstruction.ie/wp-content/uploads/2017/11/1D2O0844-1000x600.jpg
http://precisionconstruction.ie/wp-content/uploads/2017/11/IMG_2205-1000x600.jpg
http://precisionconstruction.ie/wp-content/uploads/2017/11/IMG_2206-1000x600.jpg
http://precisionconstruction.ie/wp-content/uploads/2017/11/IMG_2171-1000x600.jpg

Project Overview

Address

St. David’s CBS, Artane, Dublin 5.

Project

Remedial works to Facades as Part of On-going Maintenance Contract Including Capital Upgrade and Remediation Projects to a Listed Building

Description Of Featured Works

Remedial repair works to rendering on external elevations, painting and decoration and replacement of water tanks to listed building at St. David’s CBS, Artane, Dublin 5.

Duration Of Featured Project

September 2009 to November 2009